Multifunctional sport room

 

Arch at the south entry of the city

the most important projects realized during Parliamentaryperiod 2005/2010

projects in the municipal plan

Project
Cost ( thousands of dinars)
Observations
1
road asphalting
1.797
the first part has been completed at a cost of 365 TD and the second part will be realized at the cost of 1432 TD
2
planning of Etaghiir city
495
achieved at 100%
3
planning of Ennassim city
470
achieved at 100%
4
planning of Bassatin I city
495
achieved at 100%
5
public lighting
380
the first part has been completed at a cost of 140 TD and the second part will be realized
6
smartening of the city
300
the first part has been completed at a cost of100 TD and the second part will be realized
7
amelioration of Awled Aziza cemetery
50
achieved at 100%
8
amelioration of the Municipal Stadium
100
90% realized
9
amelioration Wholesale market
380
Preparation of studies is in progress
10
amelioration of Municipal Warehouse
100
the process of preparing transaction files
11
Purchase of cleaning equipment
250
achieved at 100%
12
Purchase of computer equipment
45
40% realized
sum
4.862
 

Projects completed and programmed out of the Municipal plan :

Project
Cost ( thousands of dinars)
Notes
Final Rejection 5.000 preparation of studies about the effects on the environment
Expansion of sports complex traks 2.600 in the process of sorting the financial offers
amelioration of the Wadi Adarb Park 2.000 in the process of request the offers
Protection of the city from flooding 800 achieved at 100%
Purification of Bab Arayes city 400 achieved at 100%
Grassing the municipal Stadium 310 achieved at 100%
Purification of Olympic city (part 2) 200 achieved at 100%
Purification of Ennour El Gharbi city 260 achieved at 100%
achievement of wrestling hall 250 achieved at 100%
purification of Olympic city (part3) 275 under way
restoration of the ancient theater 100 achieved at 100%
sum 12.195